Standard Technical Features of BTG System for Supercritical 660/800 MW Thermal Units
22
ii) The following correction curves shall be applicable for performance test
of the ESP:
a) Inlet flue gas flow.
b) Inlet flue gas temperature.
c) Inlet dust loading.
d) Sulphur content of coal.
5.5.3 Auxiliary power consumption
The unit auxiliary power consumption shall be calculated using the following
relationship:
Pa = Pu + TL
Pa = Guaranteed Auxiliary Power Consumption.
Pu = Power consumed by the auxiliaries of the unit under the test.
TL = Losses of the transformers based on works test reports.
While guaranteeing the auxiliary power consumption, all continuously
operating unit auxiliaries shall be included and number of coal mills to be
considered in operation shall be as per requirement of design coal.
5.5.4 Performance/ acceptance test for turbine generator
i) Performance test for the turbine generator set will be conducted in
accordance with the latest edition of ASME PTC-6.
ii) Power consumed by the integral auxiliaries mentioned which is to be
deducted from electrical power generated, shall be measured during the
performance/ Acceptance Test. Wherever the measurement is not
possible, design values of power consumption by an auxiliary shall be
considered.
iii) Corrections to the test results for steam turbine shall be applied as per
the correction curves provided. When the system is properly isolated for
a performance test, the unaccounted for leakages should not be
more than 0.1% of the design throttle flow at full load. However, during
the test, if it is found that the unaccounted for leakage is more than 0.1%
of design throttle flow at full load, then heat rate will be increased by an
amount equal to half the difference between actual unaccounted for
leakage expressed as percentage of design throttle flow at full load and
0.1% (allowed by the code). In case excessive leakage is visible in the
plant area, the source of leakage shall be identified and attended before
commencement of the test.
iv) The tests shall be arranged in a manner that the normal unit operation is
not disrupted. Duplicate test runs shall be performed at 100% TMCR
and 80 % TMCR loads. The results of corrected heat rate shall agree
within 0.25% and average of two shall be considered heat rate achieved.