Standard Technical Features of BTG System for Supercritical 660/800 MW Thermal Units
18
v) When one half of the condenser is isolated, condenser shall be capable of
taking at least 60% T.G. load under TMCR conditions.
vi) The design capacity of each vacuum pump in free dry air under standard
conditions at a condenser pressure of 25.4 mm Hg (abs) and sub cooled
to 4.17
0
C below the temperature corresponding to absolute suction
pressure shall be demonstrated. Correction curves for establishing the
capacity at site conditions shall also be furnished.
vii) The air and vapour mixture from air cooling zone of condenser shall be
4.17
0
C below the saturation temperature corresponding to 25.4 mm Hg
(abs) suction pressure. Correction curves for establishing the same at site
conditions shall also be furnished.
viii)
2
Pressure drop across terminal points of condenser cooling system with
on line condenser tube cleaning system in operation.
5.4.17 Feed water heaters and deaerator
The following parameters shall be demonstrated:
i) TTDs and DCAs of feed water heaters shall be demonstrated as per
guaranteed heat balance diagram for 100% TMCR condition.
ii) Outlet temperature from final feed water heater(s).
iii) Difference between saturation temperature of steam entering the
deaerator and temperature of feed water leaving the deaerator shall be
demonstrated as per guaranteed heat balance diagram for 100% TMCR
condition.
iv) Continuous and efficient operation and performance of feed heating
plant without undue noise and vibrations at all loads and duty conditions.
5.4.18 HP & LP bypass system capabilities
The design capacity of HP/ LP bypass system shall be demonstrated. Further,
the HP & LP bypass system should satisfy the following functional
requirements under automatic interlock action. It should come into operation
automatically under the following conditions:
i) Generator circuit breaker opening.
ii) HP & IP stop valves closing due to turbine tripping.
iii) Sudden reduction in demand of external load (load throw off).
2
Applicable in case CW pumps are included in scope of BTG system.